Monday, January 28, 2013

28 Jan 2013

TNB Substation formwork and rebar completed awaiting Inspection from TNB.


Thursday, January 24, 2013

24 Jan 2013

ECC SECTION 2 TAKEN ON 22ND JAN 2013
ECC RESULTS FOR SECTION 2 RECEIVED FROM JURUKUR CHAI
BUT STILL 11 PILECAPS INCOMPLETE (circled pilecaps)

 CONCRETING FOR 14 PILECAPS ON SECTION 2


SECTION 2 AWAITING ECC RESULTS, IMMERSED IN WATER


SECTION 3 EXCAVATION IN PROGRESS


Tuesday, January 22, 2013

22 Jan 2013

5 or more ?pcaps
?/110
?%
machinery
10 wheel lorry and excavator hitachi

 TNB Substation formwork and rebar in progress

ECC RESULTS ANALYZED BY JEREMY FROM YAA AND PARTLY CONFIRMED THE PILECAPS THAT CAN BE CASTED.

(1st ECC (SECTION 1 ) taken by Jurukur Chai =12 Jan 2013) 

ECC RESULTS FROM SURVEYOR =19Jan 2013

ECC RESULTS PARTLY CONFIRMED BY YAA=22Jan 2013




Monday, January 21, 2013

21 Jan 2013

5 or more ?pcaps
?/110
?%
machinery
10 wheel lorry and excavator hitachi

 TNB Substation formwork and rebar in progress

Pilecaps awaiting ECC results(confirmed at 4 pm)
Excavation of pilecaps at Section 3
TNB Substation formwork and rebar in progress


Saturday, January 19, 2013

19Jan 2013


5 or more ?pcaps
?/110
?%
machinery
10 wheel lorry and excavator hitachi


ECC RESULTS FINALLY (RECEIVED FOR SECTION 1) 
 BUT STILL HAVE TO WAIT TILL MONDAY (AFTER CHECKING BY YAA)

Friday, January 18, 2013

18Jan 2013

5 pcaps
57/110
51.8%
machinery
10 wheel lorry and excavator hitachi


STILL AWAITING ECC RESULTS FOR SECTION 1

FROM JURUKUR CHAI
SURVEY TAKEN ON  12 JAN 2103


Excavation for section 3 starts.



Backfilling of earth for Substation