Thursday, January 24, 2013

24 Jan 2013

ECC SECTION 2 TAKEN ON 22ND JAN 2013
ECC RESULTS FOR SECTION 2 RECEIVED FROM JURUKUR CHAI
BUT STILL 11 PILECAPS INCOMPLETE (circled pilecaps)

 CONCRETING FOR 14 PILECAPS ON SECTION 2


SECTION 2 AWAITING ECC RESULTS, IMMERSED IN WATER


SECTION 3 EXCAVATION IN PROGRESS