A low cost project in Teluk Air Tawar by Welcome Properties Sdn Bhd
Monday, January 28, 2013
Friday, January 25, 2013
Thursday, January 24, 2013
Tuesday, January 22, 2013
22 Jan 2013
5 or more ?pcaps
?/110
?%
machinery
10 wheel lorry and excavator hitachi
TNB Substation formwork and rebar in progress
ECC RESULTS ANALYZED BY JEREMY FROM YAA AND PARTLY CONFIRMED THE PILECAPS THAT CAN BE CASTED.
?/110
?%
machinery
10 wheel lorry and excavator hitachi
TNB Substation formwork and rebar in progress
ECC RESULTS ANALYZED BY JEREMY FROM YAA AND PARTLY CONFIRMED THE PILECAPS THAT CAN BE CASTED.
(1st ECC (SECTION 1 ) taken by Jurukur Chai =12 Jan 2013)
ECC RESULTS FROM SURVEYOR =19Jan 2013
ECC RESULTS PARTLY CONFIRMED BY YAA=22Jan 2013Monday, January 21, 2013
Saturday, January 19, 2013
19Jan 2013
?/110
?%
machinery
10 wheel lorry and excavator hitachi
ECC RESULTS FINALLY (RECEIVED FOR SECTION 1)
BUT STILL HAVE TO WAIT TILL MONDAY (AFTER CHECKING BY YAA)
Friday, January 18, 2013
Tuesday, January 15, 2013
Monday, January 14, 2013
Sunday, January 13, 2013
13 jan 2013
13 Jan 2013
Only excavator (shift cut piles out of pilecaps)
Lorry driver sick
12 Jan 2013 (1st ECC (SECTION 1 ) taken by Jurukur Chai on 12 Jan 2013)
6pcaps
33/110
lift 1/1
30.0%
machinery
10 wheel lorry and excavator hitachi
11 Jan 2013
6pcaps
27/110
lift 1/1
24.5%
machinery
10 wheel lorry and excavator hitachi
10 Jan 2013
4pcaps plus lift 1/2(completed)
21/110
lift 1/1
19.1%
machinery
10 wheel lorry and excavator hitachi
9 Jan 2013
4pcaps
17/110
lift 1/1
15.5%
machinery
10 wheel lorry and excavator hitachi